Iberdrola Australia’s proposed 136.8 MVA gas turbines
Overview
As South Australia’s sole electricity distributor, SAPN has the mission-critical role of building and maintaining the infrastructure to deliver power to over 900,000 homes and businesses. As new generating systems are submitted for connection to the grid, SAPN must conform to all rules and requirements to always ensure the ongoing secure and stable operation of the power system.
The proposed Bolivar Power Station (BPS) generating system owned by Iberdrola Australia SAGT Pty Ltd (Iberdrola Australia) contains 4 x TM2500 GE gas turbines. The BPS site is located at the end of a 1.6 km long 66 kV single circuit feeder from Parafield Gardens West Substation. BPS is comprised of 4 x 34.222 MVA generators and the agreed capacity at the connection point is 127.5 MW at 5°C.
Iberdrola Australia evaluated the technical compliance of BPS in accordance with National Electricity Rules (NER). The technical assessments included transient stability, load flow, power quality and short circuit studies to demonstrate plant compliance with the relevant NER access standards proposed.
SA Power Networks (SAPN) is the Network Service Provider (NSP) for the BPS connection and was the client for the due diligence of the above assessment by Iberdrola Australia.
Challenge
As part of the AEMO – Australian Energy Market Operator – connection process, an independent due diligence assessment of Iberdrola Australia’s connection package was required before the connection package could be submitted to AEMO for approval, and ultimately for it to be connected to the grid.
Project Solution
The due diligence was done, on behalf of SAPN, on the following connection package supplied by Iberdrola Australia:
The power system design and settings datasheets
The voltage control strategy (VCS)
The generator protection report
The PSS/E models, RUG and DMAT
The PSCAD models, RUG and DMAT
The PSS/E vs PSCAD benchmarking report
The connection studies technical report
The Generator Performance Standard (GPS) template for consistency with the connection study report and simulated test
Results
The tasks for the due diligence assessment included:
SMIB and NEM case setup
NER Clause – S5.2.5.1 Reactive power capability
NER Clause – S5.2.5.2 Quality of Electricity Generated
NER Clause – S5.2.5.3 Generating unit response to frequency disturbance
NER Clause – S5.2.5.4 Generating unit response to voltage disturbances
NER Clause – S5.2.5.5 Generating system response to disturbances following contingency events
NER Clause – S5.2.5.7 Partial load rejection
NER Clause – S5.2.5.8 Protection of generating systems from power system disturbances
NER Clause – S5.2.5.11 Frequency control
NER Clause – S5.2.5.12 Impact on network capability
NER Clause – S5.2.5.13 Voltage and reactive power control
NER Clause – S5.2.5.14 Active power control
NER Clause – S5.2.8 Fault Current
PSCAD Model and Benchmarking Assessment
Reporting
PSC Advantage
PSC has extensive experience performing grid connection studies for connections to the NEM. PSC’s experience includes working for developers, generator owner/operators, NSPs and AEMO in the development of the connection application (including the GPS) and supporting the project through the GPS negotiation phase, generator registration (R1) and generator PA12534 PSC Proposal for SAPN Penfield BESS Due Diligence commissioning (R2) phase. PSC also works with several NSPs and AEMO to perform due diligence on new and modified generator applications.
“As a network service provider, we ensure all generation connections are safely integrated into SA’s distribution network to maintain power system security and stability, and compliance to all relevant rules and regulations is of critical importance for SAPN. This requires comprehensive due diligence on the connection packages prepared by potential generation developers and consultants. It’s our experience that PSC has the right people with the experience and capabilities to support our team with the analysis required in a proficient and consistent manner.”